Most residential fences between neighbors take 1 to 2 days to install. The full project, from your first estimate to the final walkthrough, takes longer because of scheduling, neighbor conversations, HOA approval, and utility marking. Here’s how both timelines work on the fences we build every week across the Sacramento region.
“Most residential fences between neighbors take one to two days to complete, depending on the length, how rocky the soil is, and the complexity of the fence style.”
— Dominic Vella, Owner, Fantastic Fence (CSLB #979657)
How Many Feet of Fence Can a Crew Install in a Day?
About 80 feet per day for one of our two-person crews, on most wood, chain link, ornamental iron, and vinyl fences. That’s a good average for a residential project. A 60-foot shared line is usually a one-day job, and a 150-foot backyard is closer to two. On very large jobs, where the crew is on site for several days, they can set up their process for the longer run and pick up speed.
What Decides Whether a Fence Takes One Day or Two?
Length, soil, and style do most of the work, with tear-out and gates close behind.
|
Factor |
Closer to 1 day |
Closer to 2+ days |
|
Fence length |
Up to about 80 feet |
Well over 80 feet, or several runs |
|
Soil |
Soft, clear ground |
Rock, hardpan, tree roots, or old concrete footings |
|
Fence style |
Dog-ear good neighbor fence |
Board-on-board, cap & trim, horizontal, or lattice top |
|
Old fence |
No old fence, or a short run to remove |
A long run with concrete-set posts to break out and haul |
|
Gates |
One standard walk gate |
Several gates or a wide double drive gate |
|
Access |
Open access to the fence line |
Tight side yards or locked gates where materials are hand-carried |
Rocky soil is the factor nobody can see from the street. A post hole that takes a few minutes in soft ground can take much longer when the crew hits rock, roots, or a footing somebody poured decades ago. Big trees matter too: a fence line running through mature oak roots may need posts shifted a few inches on the spot. That’s why an estimator walking the line gives you a better timeline than a phone quote. On style, a dog-ear good neighbor fence is the quickest build; every extra layer or trim piece adds fitting time.
What Do Customers Say About Their Installation Time?
Here’s what a few of our customers said about their install day, in their own words:
“Installation crew was on time and finished in one day. FF had the utilities come out and mark the underground lines before construction. Very pleased with the overall installation of the fence. They had to accommodate a large oak tree and it looks good.”
— Kevin Knauss, Google review
“They removed the old fence and installed the new fence in one day. The new fence looks great.”
— Steven Herrera, Google review
“The 2-man team quickly removed and disposed of the old shared fence and took only one day to install the new fence and the second day did the same process for the second fence.”
— Pam Vaillancourt, Google review
“Their crew was courteous, and got our fence installed and everything cleared & cleaned up in a day.”
— Jackie Roush, Google review
What Happens on Fence Installation Day?
The crew removes the old fence, sets the posts, builds the fence, hangs the gates, and cleans up, usually in that order.
- Morning walk-through (about 10 minutes): You walk the fence line with the crew to confirm the fence location and gate placement. Then you can go about your day.
- Tear-out and haul-away: The old fence and its posts come out and leave with us.
- Posts: Holes are dug and posts are set. More than 80% of our wood fences go in on Bolt-Up Hidden Steel Posts, which look like wood but won’t rot.
- Build: Rails and boards go up. We build every wood fence on site, never from pre-assembled panels.
- Gates: Gates are hung, squared, and adjusted so they swing and latch properly. See our gate installation page.
- Clean-up and final walkthrough: We clean up like guests on your property. The foreman walks the finished fence with you if you’re home; if not, we call the next day to make sure you’re happy.
How Long Does It Take to Replace an Existing Fence?
About the same as a new fence: tear-out adds time, but an established fence line saves layout time. Breaking out old concrete-set posts is often the slowest single task, especially on a long run.
Plan for one practical detail: your yard may be open between tear-out and the new fence going up. If you have dogs or small kids, ask the crew how the opening will be handled and whether it will stay open overnight on a two-day job.
How Long Does the Whole Fence Project Take, Start to Finish?
Longer than installation, and most of that time happens before the crew arrives. The steps before installation day usually look like this:
- Free estimate: An estimator walks the fence line, measures, and checks soil, access, and gate locations. If you’re busy, our estimator can come at the scheduled time and walk it with you over the phone.
- Neighbor conversation: On a shared fence, agree on style, height, and cost split with your neighbor. This conversation can take longer than the installation itself, so start it early.
- HOA approval: If you have an HOA, getting approval is the homeowner’s job. We provide the drawings and specs for your application.
- Utility marking: Before anyone digs, the underground utilities are marked through USA North 811, which requires at least two working days’ notice.
- Scheduling: You get a spot on the install calendar.
An honest note on that last step: we’re usually booked out. Dominic tells customers it’s great, affordable, or fast: pick two. We’re not fast, so you get great and affordable. For the full prep checklist, see what to do before building a fence, and check local height rules with our Fence Ordinance Quick Links.
Does the Fence Material Change the Installation Time?
Less than most people expect.
- Wood fences: Built on site board by board. Simple styles go fast; detailed styles add time.
- Vinyl fences: Panels go up quickly, but post spacing has to be exact, so the time goes into layout.
- Chain link fences: Efficient on long runs and open ground.
- Ornamental iron and Durabond steel: Standard sections install quickly; custom work adds time before install day.
An automated gate runs on its own schedule because of the electrical work, opener, and safety testing, so plan it as a separate project.
Does Sacramento Weather Affect the Installation Schedule?
Yes, at both ends of the year. Heavy winter rain saturates the soil and makes digging slow and messy, so a wet week can push an install day. In summer, Cal/OSHA heat rules for outdoor work kick in at 95°F, which can move start times earlier. If weather shifts your date, you’ll hear it from us.
How Can You Keep Your Fence Installation on Schedule?
- Lock in style, height, and gate locations before materials are ordered.
- Settle the plan and cost split with your neighbor early.
- Start HOA approval as soon as you have a design.
- Point out private lines that 811 doesn’t mark: landscape irrigation and lighting, gas to a barbecue or pool heater, and power to a shed or detached garage. Hitting one is a common cause of a mid-job stop.
- Avoid design changes after materials are ordered.
- Clear furniture, planters, and stored items away from the fence line, and trim back vines and low branches.
- Secure pets, and arrange access to your neighbor’s side if the crew needs it.
- Stay reachable by phone during the install.
Frequently Asked Questions
How long does it take to install a fence?
Most residential fences between neighbors take 1 to 2 days to install, depending on length, soil, and style.
Can a fence be installed in one day?
Yes, often. A single shared line or side yard with a simple style and cooperative soil is commonly finished, cleaned up, and walked through in one day.
Do I need to be home during fence installation?
No, just for the 10-minute morning walk-through. Stay reachable by phone after that.
Does staining a new wood fence add time?
It’s a separate step, not part of installation. Redwood doesn’t require stain. If you want one, it’s applied after the fence is up and the wood has had time to dry.
What should a fence contract say about timing?
An approximate start date and completion date. The California Contractors State License Board advises that home improvement contracts list both, along with the work and materials included, who obtains any required permits, and who handles cleanup.
How much will my fence cost?
It depends on footage, style, height, gates, and soil. For a quick starting number, use our Fence Price Calculator, then book a free estimate for a flat price with zero hidden fees. Financing is available.
Get a Timeline for Your Fence
The only way to get a real timeline is to have someone walk your fence line. Fantastic Fence is licensed, bonded, and insured under CSLB License #979657, and our installs are done by 35+ background-checked W-2 employees, backed by a written guarantee: the job isn’t finished until you give us the thumbs up. We serve Sacramento, Placer, El Dorado, Yuba, Yolo, and Nevada counties. Book your free estimate online or call the office nearest you:
- Rocklin: (916) 790-7100
- Sacramento: (916) 248-5518
- Elk Grove: (916) 345-0142
Reviewed by Dominic Vella, owner of Fantastic Fence, CSLB #979657.